Construction update: weeks of 7/5/21 and 12/7/21 | Colombia

0


See a PDF version of this week’s update

What is happening

Colombia Business School

Site 7 (West Site)

  • Interior fittings (walls, glass partitions, ceilings, floors, carpentry, GFRG) and mechanical, electrical and plumbing (MEP) installations on the ceiling on floors 1 to 11
  • MEP commissioning
  • Three construction cars are in service
  • Furniture delivery

Site 6B (East Site)

  • Completion of installations of GFRC units on the exterior walls of floors 2 to 8
  • Interior fittings (walls, glass partitions, ceilings, floors, carpentry, GFRG) and MEP overhead installation on floors 2 to 8
  • Three construction cars are in service
  • Furniture delivery

Activity Below Ground Level / W. 131st Street Utilities

  • Work on the loading dock is progressing
  • The ceiling of the truck ramp is being plugged and taped
  • Painting is in progress throughout

Open spaces between 130th and 131st streets and along 12th Avenue

  • Continuation of the living roof layer
  • Structural backfill, rebar, formwork and concrete finish slab in progress
  • Installation of electrical conduits, paving stones and trench drains
  • Hanover cobblestones / hardscape are underway

600 West 125th Street

  • The contractor will drill piles to support the excavation and pour the concrete for the soldier piles
  • The contractor will fill the test pits on the south side of the site

Please note that all activities are subject to change based on weather and other field conditions.

What to expect

Construction activity

  • Regular weekday working hours: 7 a.m. to 6 p.m. Saturday and Sunday working hours: 7 a.m. to 5 p.m. After-hours permit issued for the start of construction at 6 a.m. to allow physical distancing of workers at entry to the site. Permit outside opening hours issued from 6:00 p.m. to 11:00 p.m. Monday to Friday for the installation of exterior walls to be carried out in the buildings of the business school.
  • Equipment deliveries to the site are underway

Temporary impacts on traffic and transport

  • Refer to road signs for the west side of Broadway from 129th to 130th Street – parking is permitted after 6:00 p.m. and on weekends
  • W. 131st Street between Broadway and 12th Avenue is open to one-way westbound traffic
  • The parking lane will be closed on the south side of 125th Street W, from Broadway to St. Clair Place. Parking will not be available on the south side of W. 125th Street from Broadway to the center block in front of the full length of the 600 W. 125th Street construction fence.



Source link

Leave A Reply

Your email address will not be published.